Overview
To assure production quality of the EGI Infrastructure, every cloud management framework (Cloud platform) or middleware piece (Compute, Storage, etc.) supported by Production Resource Centres needs to fulfil certain requirements. The goal of this procedure is to assure EGI Infrastructure compliance.
Definitions
Please refer to the EGI Glossary for the definitions of the terms used in this procedure.
The key words "MUST", "MUST NOT", "REQUIRED", "SHALL", "SHALL NOT", "SHOULD", "SHOULD NOT", "RECOMMENDED", “MAY", and "OPTIONAL" in this document are to be interpreted as described in RFC 2119.
Entities involved in the procedure
- Technology Provider (TP): person representing or leading Technology Provider team
- EGI Operations (EGIOps)
- Operations Centre (OC)
- Resource Centre (RC)
- Operations Management Board: EGI operations policy board
Prerequisites
Before sending a request:
- OC has to have
- the support of TP with effort to integrate with EGI Infrastructure (information system, accounting, monitoring etc), provide support via GGUS and maintain software via UMD
- one or more RC available to deploy the new platform
- TP has to have
- effort to integrate with EGI Infrastructure (information system, accounting, monitoring etc), provide support via GGUS and maintain software via UMD
- the support of one or more OC, with one or more RC available to deploy the new platform and the integration-software developed by the TP
Triggers
Steps
Request submission and validation
The request can be send by:
- Operations Centre
- EGI Operations
- Technology Provider
Resource Centres can also request integration of new cloud management framework or middleware. Such request should be first approved by Operations Centre, it belongs to. In such case OC is responsible to create a ticket on behalf of RC.
Step | Action on | Action |
---|---|---|
1 | Applicant | Opens a GGUS ticket to Operations to start the process.Subject: Request for integration of XXX to EGI Production Infrastructure (PROC19) Dear Operations, We would like to request for starting procedure of integrating XXX to EGI Production Infrastructure: |
2 | EGIOps | Operations contacts the OMB to request the approval of the request. |
Functional requirements
Functional requirements for new product to be integrated:
- support VO concept
- support X.509 certificates and/or federated identities (i.e. be compatible with EGI Check-in)
Integration steps
Integration covers following areas (where possible steps can be done in parallel):
# | Responsible | Action | Additional temporary comments |
---|---|---|---|
0a | EGIOps | When Approved, EGIOps and TP should agree on Underpinning Agreement (UA) | agree on Corporate-level Technology Provider Underpinning Agreement or on a customised version |
0b | EGIOps | Set up an integration Task force for given Technology Product composed of:
|
Configuration Management
# | Responsible | Action | Additional temporary comments |
---|---|---|---|
1a | GOCDB | Add new service types agreed within Task Force. | |
1b | Pilot Site | Deploy technical service instance and register in GOCDB. |
Information System
# | Responsible | Action | Additional temporary comments |
---|---|---|---|
2a | Technology Provider | Develop software for integration with BDII. | Analyse the use cases for deciding if the new technology has to be published in the BDII or not, and the relevant set of information to publish.
|
2b | Pilot Site | Deploy software for integration with BDII and documentation. | |
2c | EGI Operations | Verify integration | Alessandro Paolini, Enol Fernandez, Baptiste Grenier, Operations checks documentation |
Monitoring
# | Responsible | Action | Additional temporary comments |
---|---|---|---|
3a | Technology Provider | Develop nagios probe with support from SAM team and documentation. | ARGO Guidelines for monitoring probes |
3b | ARGO, EGI Ops | Check probe, verify results, add to SAM release. Add test to ARGO_MON profile. | PROC06 and PROC07 |
3c | ARGO, EGI Ops | Deploy probe in production and publish documentation. | Operations checks documentation |
3d | ARGO, EGI Ops | if the new technology needs to be monitored by secmon and pakiti, add the related tests in the SEC_MONITOR profile. | Operations verify that the security tests are properly executed |
Operations (ROD) Dashboard
# | Responsible | Action | Additional temporary comments |
---|---|---|---|
4 | EGI Ops | Add test to Operations profile (PROC06 Setting a Nagios test status to OPERATIONS) |
Support
# | Responsible | Action | Additional temporary comments |
---|---|---|---|
5a | Technology Provider | Declare Quality of Support for 3rd level Support Unit (SU) and name of SU | |
5b | GGUS | Create Support Unit under "Product Teams" category |
Accounting
# | Responsible | Action | Additional temporary comments |
---|---|---|---|
6a | Technology Provider | Develop software for integration with APEL | Define integration and what data should be published.
|
6b | APEL | Validate integration | EGI Operations checks documentation |
6c | EGI Accounting Portal | Display data |
UMD
# | Responsible | Action | Additional temporary comments |
---|---|---|---|
7a | Technology Provider | Ensure software developed for the integration of the new Technology Product satisfies UMD Minimal Requirements as described in Instructions for Technology Providers | |
7b | EGI Ops (UMD representative) | Technology Provider info is added in Technology Providers List and UMD Product ID card | |
7c | EGI Software provisioning Team | Applies the UMD Software Provisioning process to assess the quality of the new product | |
7d | EGI Ops (UMD representative) | Once confirmed a successful provisioning (step 11c) includes the new product/products into an UMD release and makes it available to the production infrastructure, in the UMD repositories |
Documentation
# | Responsible | Action | Additional temporary comments |
---|---|---|---|
9a | EGI Ops | Update relevant documentation | |
9b | Technology Provider | Develop documentation for users and admins where missing | |
9c | EGI Ops | Validate Documentation |
Security
# | Responsible | Action | Additional temporary comments |
---|---|---|---|
11a | Technology Provider | complete the EGI SVG Software Security Checklist | A brief written response to Chair of SVG (Linda.Cornwall <AT> stfc.ac.uk) is requested |
11b | Security team | Provide recommendations based on provided input | |
11c | Technology Provider | Implement recommendations | |
11d | Security Team | Validate implementation of recommendations |
The Announcement
EGI Ops announces the availability of new product to OMB and includes the announcement in the monthly EGI Broadcast to communicate the availability of the new product to NGIs, VOs, RCs managers.