Page properties | ||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
...
Expand | ||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Table of contents
Table of Contents | ||||
---|---|---|---|---|
|
...
- Applicant. The Applicant submits a request for changing the EGI OPS profile. Anybody is allowed to submit the request. The request is submitted to the respective Operations Centre, who after acceptance, forward it to the Operations Management Board (OMB) for discussion.
- Operations Centre. The entity associated to EGI that is responsible of delivering local operational services to a Resource Infrastructure Provider. In order to contribute resources to EGI a Resource Infrastructure Provider must be associated to an Operations Centre.
- Resource Infrastructure Operations Manager. Represents the respective Resource Infrastructure within the OMB.
- EGI Operations team. Team coordinating EGI Infrastructure.
- ARGO Team. The ARGO Team is responsible of scheduling, integrating and releasing probes.
Pre-requirements
- This procedure requires usage of the ARGO system for generating monthly availability and reliability statistics. Detailed information about ARGO system can be found on the following link: http://argoeu.github.io/overview/.
- If the request of change includes the addition of new tests, each test MUST first be integrated with the Operations Dashboard, i.e. being an OPERATIONS test included in the ARGO_MON_OPERATORS profile is a necessary condition to be included in the ARGO_MON_CRITICAL profile for A/R computation (see procedure PROC06). This should ensure that the new probe has been tested on the production sites, excluding the occurrence of anomalies not strictly depending on the sites.
- EGI software teams are responsible for the development and testing of new probes.
Steps
Step | Action on | Action |
---|---|---|
1 | Applicant | Sends a change request to the attention of the respective own Operations Centre. The request is submitted through a GGUS ticket. Use the "Affected ROC/NGI" to address the ticket to the appropriate Operations Centre. Template: Subject: Request for adding/removing XXX(,YYY,...) test(s) to/from the EGI OPS A/R Profile We would like to request adding/removing XXX(,YYY,...) test(s) to/from from the EGI OPS Profile Prerequisite data: * name of ARGO test(s): * name of service on which the test runs: * link to documentation page: * motivation (which part of the infrastructure will be improved with the new test or description of users' problems which will be avoided in future - provide list of GGUS tickets is possible) |
2 | Operations Centre | The Operations Centre process the request specified in the GGUS ticket for acceptance/rejection. Motivations for rejection need to specify in the GGUS ticket. In case of acceptance, a GGUS ticket is opened to EGI Operations Support Unit to forward the request for discussion in the OMB. Template: Subject: Request for adding/removing XXX(,YYY,...) test(s) to/from the EGI OPS Profile We would like to request adding/removing XXX(,YYY,...) test(s) to/from the EGI OPS Profile. Please see details in GGUS ticket _link to Applicant's GGUS ticket_. |
3 | EGI Operations team and Resource Infrastructure Operations Manager | EGI Operations team schedules a presentation of the change requested at the next possible OMB meeting. The relevant Resource Infrastructure Operations Manager presents the request during the meeting. The Applicant is invited to attend the meeting. Only one request will be processed at a time as the impact of a change needs to be assessed. Requests are processed depending on their priority, as agreed by the OMB. |
4 | EGI Operations team | Opens a GGUS ticket to "Monitoring (ARGO)" requesting the addition (or removal) to the ARGO_MON_CRITICAL profile. |
5 | ARGO team | Implements the change on the agreed date (generally, the first day of the month). |
6 | EGI Operations team | Before closing the ticket, verifies there are no anomalies with the new A/R reports and report back to the NGI Managers by email or to the next OMB meeting. |
7 | EGI Operations team | Broadcasts the modification to all relevant parties (i.e. Operations Centres and Resource Centres) through the next Monthly Broadcast. Closes the GGUS ticket |
...